Stay informed about the latest developments happening at the exciting new ArcoVia Park Place construction project, from its groundbreaking beginning all the way through to its eagerly anticipated completion.
Progress Update
35%
Excavation Works
Completed
Civil / Structural / Architectural Works
Rebar works and formworks enclosure for columns and shear wall at G/F-2/F
Installation of bentonite and PVC water stop at retaining wall termination
Mechanical Works
Complete checking of layout of mechanical blockouts for G/F
Electrical Works
Installation of roughing-ins at G/F column and shear wall